Rosyth Dockyard 7 – 1910 The Submarine Basin


< 6 – Construction contracts Δ Index 8 – 1910–1911 The North Wall of the Inner Basin and Graving (Dry) Docks >

 

This was the most straightforward part of the construction – creating seawalls and jetties, then excavating the basin.

By April 1910, a clay embankment had been built round the area that would form the submarine basin and it had been pumped out. Foundation trenches were dug for the basin walls, the foundations were laid, and concrete walls constructed.

The basin area was then excavated with the dry spoil being used to reclaim the land north of this basin.
The submarine basin was excavated to give a depth of water of 15ft (4.6m) at low water spring tide, i.e. the lowest low tide mark.


< 6 – 1909 Awarding the construction contracts Δ Index 8 – 1910–1911 The North Wall of the Inner Basin and Graving (Dry) Docks >

NQHT has completely revised this website. We would like to know how the website is being used by counting the number of visits to each webpage. We are NOT gathering information about individuals!

Please select "Accept" if you are happy for us to use tracking cookies to count the number of visits to each page.

If you select "Decline", you can visit the NQHT website, but no data will be gathered, so we will have less accurate information about the value of the website :-(

Once you have made a choice, this message will disappear but will return every 30 days to allow you to verify your choice.