Rosyth Dockyard 11 – 1914 Completing the Main Basin


< 10 – 1914 Construction progress at the outbreak of war Δ Index 12 – 1914-1916 The Entrance Lock >

 
To bring the main basin into use, the sea wall had to be completed, and the basin excavated.

The east wall was constructed behind the main basin temporary clay dam after the main basin had been excavated. Trenched were dug from the excavated base of the basin and lined with timber to hold the poured-concrete foundations. At one point the bottom of this foundations trench was 70ft (21m) below Ordnance datum. The same technique was used to build the north wall and graving docks, with trenched being dug down from the original sea-bed level.

The west and south walls were nearing complete on on top of their concrete monolith foundations
But before the basin could be flooded, the entrance lock and emergency exits had to be completed.


< 10 – 1914 Construction progress at the outbreak of war Δ Index 12 – 1914-1916 The Entrance Lock >

NQHT has completely revised this website. We would like to know how the website is being used by counting the number of visits to each webpage. We are NOT gathering information about individuals!

Please select "Accept" if you are happy for us to use tracking cookies to count the number of visits to each page.

If you select "Decline", you can visit the NQHT website, but no data will be gathered, so we will have less accurate information about the value of the website :-(

Once you have made a choice, this message will disappear but will return every 30 days to allow you to verify your choice.