Rosyth Dockyard 8 – 1910-1911 The North Wall of the Inner Basin and Graving (Dry) Docks


< 7 – 1910 The Submarine Basin Δ Index 9 – 1912-1913 The Main Basin Sea Walls >

 

While work proceeded on the submarine basin, a second clay embankment was constructed round the site of the north wall of the main basin and the three dry docks. The embankment was complete and this area pumped out by April 1911.

Trenches were dug, and lined with timber to hold the concrete foundations for the walls of the basin and the graving docks.

By the end of 1911, the north wall was complete from the north-west corner of the basin to the No. 1 Dock entrance. Docks No. 1 and 2 had been excavated, and the walls and floor completed.

Dock No 1, looking towards the inner basin

The entrance to No 2 Dock c 1914

Work then began on Dock No.3.

The north wall and entrance to No 3 dock c 1915
Work is underway to excavate the floor of the basin.


< 7 – 1910 The Submarine Basin Δ Index 9 – 1912-1913 The Main Basin Sea Walls >

NQHT has completely revised this website. We would like to know how the website is being used by counting the number of visits to each webpage. We are NOT gathering information about individuals!

Please select "Accept" if you are happy for us to use tracking cookies to count the number of visits to each page.

If you select "Decline", you can visit the NQHT website, but no data will be gathered, so we will have less accurate information about the value of the website :-(

Once you have made a choice, this message will disappear but will return every 30 days to allow you to verify your choice.